Wasa Dredging have signed a contract for dredging and blasting of the Oslo Fairway. "Innseiling Oslo" consists of 20+ areas of bedrock to dredge and is calculated to last for about half a year....
Wasa Dredging started working in Ålesund, Norway. The project consists of blasting and dredging of four areas of bedrock....
Wasa Dredging has finished the project in Pietarsaari Fairway. WD removed about 970 000 m3 hard moraine, clay and sand. WD also removed over 100 big stones and boulders during the project ranging from 5 m3 to 60 m3. Equipment Used: Optimus, Hector, Boulder, Dana II &...
Wasa Dredging has as of December 23rd completed the project in Uusikaupunki, Finland. The project included 98 000 m3 of rock blasting, 399 000 m3 of dredging of blasted rock aswell as 434 000 m3 dredged moraine. The project was completed according to schedule....
The project consists of underwater blasting of 40 000 m3 rock, dredging of 90 000 m3 blasted rock and dredging of 180 000 m3 soil. The contract also includes covering of polluted soil with clean soil, the building of a rock bank for storing of contaminated...
The project in Pietarsaari Harbour is now completed as of fall 2014....
Newly built backhoe dredger "Optimus" has started working in Pietarsaari Harbour....
Wasa Dredging now have an official Facebook page. You can find the page by following the link: www.facebook.com/wasadredging...