December 2014 – Uusikaupunki project complete

December 2014 – Uusikaupunki project complete

Wasa Dredging has as of December 23rd completed the project in Uusikaupunki, Finland. The project included 98 000 m3 of rock blasting, 399 000 m3 of dredging of blasted rock aswell as 434 000 m3 dredged moraine. The project was completed according to schedule.